The processing timelines listed below are guidelines for operations performed individually. For multiple operations refer to paragraph at the bottom of the page.
Columns
3 Weeks
Beams (Depending on the part.)
2 Weeks
Stairs
4 Weeks
Railing
3 Weeks
Welding
2 Weeks
------
5-6 Weeks
------
4-5Weeks
------
------
3 Weeks
Paint
3 Weeks
O.S. Operations (Plating, H.T., Galv., etc.)
Add 1-2 Weeks
Powder coating
Add 1-5 days
For Core Customers orders are being accepted for
7-8 week
delivery on items involving multiple operations. This information is to be used as a general guideline in helping to plan your requirements. For specific delivery requests please consult with your project manager.